About the project
New Radio Mast in Riedlingen-Neufra
For the construction of a radio mast approximately 43 metres high, we investigated the ground conditions and assessed the site’s requirements under water legislation. Its location within a formally designated floodplain presented a particular challenge.
Challenge
To ensure safe design, it was necessary to establish the bearing capacity and characteristics of the ground, as well as whether the project could be approved within the floodplain. The excavated soil also required assessment under environmental legislation.
Our services
Our services included a geotechnical ground investigation comprising two small-diameter percussion boreholes to a depth of 6 metres, assessment of ground and foundation conditions, and preparation of a geotechnical report. We also carried out soil sampling followed by laboratory analysis in accordance with the German Substitute Building Materials Ordinance (EBV). In addition, we assessed flood risk across different flood scenarios and prepared a supporting report under Section 78 of the German Federal Water Act (WHG) to support an exemption under water legislation.
Result & Added Value
The combined geotechnical and water legislation assessment provided the client with a sound basis for foundation design and the permitting process. It also established the environmental classification of the excavated soil, enabling technical, permitting and environmental risks to be considered at an early stage.
Client
Cteam Consulting
& Anlagenbau GmbH
Location
Riedlingen-Neufra,
Baden-Württemberg
Project period
2025 – 2026